After much planning, the much anticipated hotel project began on 1st February 2010. Over the next 38 weeks the rear of The Alma will be transformed to include 23 beautiful boutique bedrooms.
Exciting (and stressful!) times lie ahead and we hope to keep you all updated on our progress as often as possible.
Follow our story here…

Sep 24

Big changes, new views & the end in sight!

Just 8 weeks to go and look at how far we’ve come! With many a set back with our typical British weather the guys are now back on track and the progress is amazing.
Check us out….

Post Pic
Sep 04

A happy goodbye to the crane

After 4 months of speedy work we have said a fond farewell to the crane. Thanks for your work but you won’t be missed!!

Post Pic
Aug 10

Moving on up!

Only 13 weeks left to go! So… The building work is almost complete, in the next week or so we will see the roof go on – we just need blue skies back to speed things up!
Heres whats going on inside…

Post Pic
Jul 15

Second floor & sneak peak at interiors!

BIG developments this week! Not only are we nearly at the end of the second floor brickwork but we are really cracking on with the the pub interior plans and they look amazing! We have visuals of the bedrooms/bathrooms mocked up ready for our brand new spanking website andour new logo and signage is being [...]

Post Pic
Jun 21

Ground Floor – Tick!

I can’t believe how far we have come in just 2 weeks. The ground floor brickwork is now complete and the steel works arrive this week. We can now see the size of the rooms and our brand new ground floor kitchen. The visuals are now up on the outside hoardings so you can see [...]

Post Pic
May 31

Week 18 – Ground Floor…

The sun is shining and we’re nearly half way there! Things are happening so quickly now and the changes are by the hour. The ground floor brickwork is being laid and time-wise we are back on track. Hurrah!

Post Pic
May 24

Phase 2!

If you want a job done properly, you can’t beat a northern company…Much to my delight, the crane was assembled by Baldwins of Leeds! A highly skilled and long job in soaring temperatures but our crane is now in place…. the real work has now begun….

Post Pic
May 04

Week 14

How can we be a third of the way ALREADY?!? We’re out of the ground at least and awaiting the arrival of the crane which apparantly means the start of the exciting stuff!!

Post Pic
May 04

Bricks and Mortar!

The laying of the first brick has been a milestone moment and we can begin to see the layout of the ground floor!

Post Pic
Apr 07

Our big sandpit!

Week 10 and things are getting interesting again! The foundations are being dug for our new basement which will house our new boiler room (this is exciting in our world!)
It is a little sad to see the end of our courtyard especially now the days are getting warmer but the end product will be worth [...]

Post Pic
Mar 31

Back to Business

A whole 3 weeks has passed and… there is still a big hole! I suspect this stage could take quite a while and not actually be very eventful!

Other news is that we have picked some amazing interiors, I am loving the beautiful Swan Lake wallpaper, part of the sylvana range by Nina Campbell for Osbourne [...]

Post Pic
Mar 13

A small break

Post Pic
Mar 01

Week 5 – a whole new view!

Can’t believe we are at the end of phase 1 already. We’re on plan and demolition complete. The site looks huge and the underpinning is ready to start.

Post Pic
Feb 22

Week 4 – Monday 22nd Feb

Rain, rain, rain… but hasn’t stopped play! The metal works is almost completely demolished and the archeological dig starts this week. Wonder if they’ll find anything?!

Post Pic
Feb 15

Week 3 – Monday 15th Feb

Nearly there!

Post Pic
Feb 11

Thursday 11th Feb

 
The walls are coming down!

Post Pic
Feb 09

Week 2 – Tuesday 9th Feb

First full site meeting today and so far we are on track. The contractors will soon be working from the flower shop offices next door alleviating any excess “Porta cabins” on Alma Road.
Today we looked at the fluffy stuff – the amazing interiors for the rooms and there were also less glamorous talks about sump [...]

Pic post
Feb 06

Saturday 6th Feb

Close to the end of Week 1 and the roof of the metal works has gone, we have a whole new view from our flat! Metal gates have been installed within the hoardings and the site is looking surprisingly neat and tidy!
 

Post Pic
Feb 04

Progress

Progress! The hoardings are nearly all up and the demolition of the metal works has begun. 2 new doors have also appeared in the pub…

Post Pic
Feb 01

The Big Start Day

Finally the big start day arrives and we rush downstairs to work expecting big happenings! Our over enthusiasm was misplaced, just one van and a few small tinkerings going on next door in the metal works!

Post Pic